KJO

KJO

Khafji

8 Exchangers

1 month

RFET, IRIS

Petrol Steel

SATORP

Jubail

Film Review

1 year

RTFI

GCC

SATORP

Jubail

Film Review

1 year

RTFI

Valentine Maritime

Manifa Pipe Laying

Manifa Offshore

Marine Line

10 months

UT Scan & UT, MT

CAT

UBTG-1

Shedgum

Pipeline

4 months

UT Scan

Yanbu Steel

Crystal

Yanbu

Vessels

3 months

RT +

Yanbu Steel

Yanbu Cement

Yanbu

Tanks

3 months

RT +

Energya

Project – 146

Rabigh

Vessels

3 months

RT +

Bemco

Bemco1

Rabigh

Columns

2 months

UT Scan

RHM

Juaimah Pipeline

Khursaniya

Pipeline

1 month

UT Scan

Hyundai

Karran Gas Factory

Khursaniya

Tie-Ins

3 months

METAPHASE

Yanbu Steel

Rabigh Power Plant

Rabigh

11 Tanks

15 months

RT +

Energya

CEMCO

Rabigh

Flares + Cans

6 months

RT +

Energya

Rabigh Power Plant

Rabigh

Pipes

6 months

RT +

Energya

S.E.T.E

Rabigh

Vessels

6 months

RT +

Energya

Bemco-157

Rabigh

Vessels

6 months

RT +

CAT

UPTG-1

Shedgum

Pipeline

1 year

RT,UT,PT, & MT

GCC

QPL Project

Al – Qassim

3rd Party Inspection

8 months

RTFI

GCC

Sales Gas pipelines

RAS Al – Khair

3rd Party Inspection

8 months

RTFI

Yanbu Steel

Sahara/Daelim

Jubail

23 Vessels

2 years

RT +

CEMC CO

Rabigh Power Plant

Rabigh

Flair & Plates

6 months

UT

Energya

SK Engineering

Rabigh

Plates

4 months

RT, UT

Energya

MMG

Rabigh

Plates

4 months

RT, UT

Al – Zamil

Hail Power Plant

Hail

Tanks

3 months

RT, PT

Energya

Zeeco

Rabigh

Vessels

6 months

RT +

Bemco Steel

Bemco

Rabigh

Columns

6 months

UT

Riyadh Refinery

Riyadh Ref New Heater

Al – Riyadh

Pipes Pre- Heating

3 months

PWHT

Samsung

SATORP

Jubail

Pipes

3 month

PWHT

NPC

Aramco

Dhahran

Manpower Supply

2 years

VT,RT,UT

Yanbu Steel

Sahara/Daelim

Y.S. Workshop

11 Tanks

1 year

RT +

Yanbu Steel

Ventech

Yanbu

Vessels/ Columns

2 years

RT +

Al – Zamil

Rabigh Power Plant

Rabigh

13 Tanks/ Water

12 months

RT +

Inma

Inma

Yanbu

 

3 months

PWHT

Qurayyah P. Plant

Bemco

Qurayyah

 

18 months

RT, MT, PT

Qurayyah P. Plant

Bemco

Qurayyah

Pipes

18 months

PWHT

Gsse

Rabigh Power Plant

Rabigh

Pipes

12 months

RT

Alsc

Rabigh Power Plant

Rabigh

Pipes

12 months

RT

Fawaz A. Bajaber

Rabigh Power Plant

Rabigh

Pipes

2 months

RT

Yanbu Steel

Samsung

Jubail

18 Tanks

2 years

RT +

Hameed Ali

Rabigh Power Plant

Rabigh

Pipes

6 months

RT

Welspun

Welspun

Dammam

 

3 months

UT

Sepco lii

Rabigh Power Plant

Rabigh

Tanks & Pipes

2 years

PWHT

Inma

Saudi Kayan Shutdown

Jubail

 

2 months

PWHT

Bemco

Riyadh Power Plant 10

Riyadh

Tanks & Pipes

1 year

RT, UT, MT

KJO

Shutdown (On & Offshore)

Khafji

Shutdown

2 months

Shutdown

G5

G5

Dammam

Pipes

6 months

RTFI

CTCI Al Zamil

Yerp/Aramco

Yanbu

5 Tanks

6 months

RT, MT, PT

Al – Bloushi Group

Yasref

Yanbu

11 Tanks

6 months

RT

Mizat

Abu Hadriah

Jubail

Pipeline

6 months

RT, MT

Fmq

Aindar

Dammam

Pipes

6 months

RT, MT

Fmq

Dammam 2nd Industrial

Dammam

Pipes

6 months

RT, MT

Sepco lii

Rabigh Power Plant

Rabigh

Pipes

1 year

PT, MT

Yuksel

Jazzan – Leith pipeline

Laith

160 Km Pipeline

1 year

RT, AUT

GTC

Riyadh Ref New Heater

Riyadh

Tanks

2 months

PWHT

Eversendai

Eversendai

Riyadh

 

2 years

UT, MT

Precision Forgings

Precision Forgings

Dammam

 

1 year

PMI, UT

Welspun

Welspun

Dammam

Pipes

1 year

RTFI

Inma

Sharq/Sabic

Jubail

Shutdown

1 month

Shutdown PWHT

Al Amara International

Sharq/Sabic

Jubail

Shutdown

1 month

RTSAFERAD, RSO, PT

Bilfal

 

Jubail

Vessels & pipes

4 months

UT, RT

Khodari

Petro Rabigh

Rabigh

Pipes

6 months

RT, UT

Petrojet

Yerp/Aramco

Yanbu

Tanks & Pipes

1 year

MT +

Petrol Steel

Sadara Chemical Company

Jubail

Tanks & Pipes

 

RT, PMI, MT

Alishar

Jazzan-Leith Pipeline

Laith

200 Km Pipeline

18 months

RT

ABV

Yerp/Aramco

Yanbu

Tanks & Pipes

1 year

RT, MT, UT

Gulf Steel Works

Yerp/Aramco

Yanbu

13 Tanks

1 year

RT, MT

Olyan Descon

Yerp/Aramco

Yanbu

Tankes & Pipes

1 year

RT, MT, UT

YSC

Yerp/Aramco

Yanbu

Tanks

2 years

RT, MT, PAUT

 

Some Running Projects

Client

Project

Location

Scope

Duration

Method

Al Amara International

Sharq/ Sabic

Jubail

 

1 year

RTSAFERAD, RSO, PT

Yanbu Steel

Lubref

Yanbu

Different

2 years

RT, MT, UT

GSCC

Wasit

Jubail

Pipes

2 years

RT, MT, PWHT

Al Swaidi

Wasit

Jubail

Pipes

2 years

RT, MT, HT, PWHT

Samsung

Pkg. 4 Ighc Project

Shaybah

Pipeline & pipes

2 years

PMI, RT, PWHT, MT, PT

Larsen & Toubro

Wasit

Jubail

Pipes

2 years

RT, MT, UT +

Hidada

 

Jeddah

Tanks & Pipes

6 months

RT, UT

Al – Sadiq

Sabic

Jubail

Pipes

6 months

RT Safe RAD

AICO

Yerp/ Aramco

Yanbu

Tanks

1 year

RT, MT, UT

Sungdo

Wasit

Jubail

Pipes

2 years

RT, MT, PMI

Dangho

SWCC

Riyadh

Tanks

2 years

RT, MT

Zamil

 

Dammam

Different

1 year

UT

KJO

Shutdown

Khafji

Shutdown

3 months

IRIS, B. Scope, API

Gusat

Sadara Chemical Company

Jubail

Different

2 years

PMI, RT, PWHT, MT

TCC

Sadara Chemical Company

Jubail

Pipes

2 years

PMI, RT, PWHT, MT

Dragados

KJO

Khafji

Pipes

1 year

RT, UT, MT, PMI

 

 

 

Copyright © 2014. Quality Control Service
P.O.Box: 4607 Al Khobar | 319252 Saudi Arabia
Office: +966 3 898 9300 | Fax: +966 3 898 9440
Info@qcs-co.com


Facebook